Independent Engineer (consulting, project management) and construction supervision duties related to the implementation of „Science Center in the Debrecen Botanic Garden” - TIOP 1.3.3/08/2-09-0002 project

Independent Engineer (consulting, project management) and construction supervision duties related to the implementation of „Science Center in the Debrecen Botanic Garden” - TIOP 1.3.3/08/2-09-0002 project

Project data:
Client: Debrecen Megyei Jogú Város Önkormányzata  (Debrecen Municipality)
Contractor: HUNÉP Universal Építőipari Zártkörűen Működő Rt.
Contract Amount: HUF 9 750 000
Construction Amount:
Lot 1: HUF 999 790 000
Lot 2: HUF 23 100 000
Lot 3: HUF 31 363 500

Start/end of Contract: 30.08.2010
Start/end of construction: 31.03.2014
End of guarantee period: 31.03.2017

Project description:
Construction supervision for the following project parts:

• Lot 1: construction of Palace of Sciences (2845.06 m2) and related development schemes

• Lot 2: reconstruction of Observatory building (68.04 m2) and Experimental Animal Building (358.45 m2).
• Lot 3: Awadukt-Thermo ground-air heat exchange system
• Lot 4: management and demolition of radioactive isotope laboratory and hazardous waste disposal facility